Andhra Pradesh - Online Apply for Temporary Electricity Supply through APEPDCL
- Step 1 : First one has to make sure that all the required documents are in hand to apply online. If you would like to know about the documents that are required for this procedure, please visit the following link : Required Documents to Apply for Temporary Electricity Supply through APEPDCL
- Step 2 : To apply for temporary electricity connection in APEPDCL online navigate to the link Apply Online
- Step 3 : Click on “LT New Connection” which is highlighted in “Red” in the below image.
- Step 4 : Choose whether the nearest electric pole is within 30 meters or not which is highlighted in “Red” in the below image.
- Step 5 : If you click “Yes” button payment details will be provided on the screen read it carefully and click on the “Close” Button which is highlighted in “Red” in the below image.
- Step 6 : If you click “No” button payment details will be provided on the screen read it carefully and click on the “Close” Button which is highlighted in “Red” in the below image.
- Step 7 : Now click on the “Submit” Button which is highlighted in “Green” in the below image.
- Step 8 : Enter all the details prompted in the new screen and click on the “Submit” Button which is highlighted in “Green” in the below image.
- Step 9 : Refer to the “Required Information” section on this procedure.
- Step 10 : Click on submit button. An OTP will be received in the given mobile number. Enter the OTP and click on submit button.
- Step 11 : Enter the General Information. Click on “Next” Button. Now enter all the details regarding the connection supply and click on submit.
- Step 12 : Upload all the required documents. Please make sure you have all the documents that are listed down the “Required Document” section of this page.
- Step 13 : Click on “Registration”. Your application is now registered.
- Step 14 : The respective authority will visit the provided site for inspection.
- Step 15 : On satisfactory inspection in all respect by the officials payment has to be done accordingly.
- Step 16 : After payment, connection will be effected according to consumer’s application.